Risk assessment in sustainability of dredging projects by considering uncertainties

Number of pages: 104 File Format: word File Code: 31316
Year: 2014 University Degree: Master's degree Category: Civil Engineering
  • Part of the Content
  • Contents & Resources
  • Summary of Risk assessment in sustainability of dredging projects by considering uncertainties

    Master's thesis in the field of civil engineering

    Soil and soil mechanics trend

    Abstract

     

    Dredging projects in urban areas are always at risk. Therefore, a suitable safety margin should be considered in the design of the guard structure. Traditional slope stability assessment methods, which are usually based on empirical judgments such as the concept of confidence factor and limit equilibrium method, do not consider uncertainties. Efforts to quantify existing uncertainties and risks led to the emergence of risk-based approaches. Reliability analysis and risk analysis are developed methods to overcome this problem. In this method, the reliability coefficient is determined based on uncertainty parameters and acceptable risk level. This method can be used for risk assessment and necessary measures to control risks. By using these methods, the risk can be assessed and necessary measures can be taken to control the risk. The Monte Carlo simulation method is one of the probabilistic evaluation tools that includes many uncertainties in order to measure the safety and stability of excavation trenches. In the current research, the safety of the nailed wall was investigated using the probabilistic method of Monte Carlo simulation, and the reliability index and probability of failure were also calculated.

    Key words: excavation, uncertainty, risk assessment, Monte Carlo simulation, nailing, reliability analysis, limit equilibrium

    Chapter 1

    General

    Chapter First-General

     

     

    1-1- Introduction

    With population growth, the need for construction increases and this is only possible with the expansion of civil infrastructures. On the other hand, the lack of high-quality land (land whose soil has suitable mechanical properties for construction) in densely populated cities, as well as the high cost of land in some areas, has caused the construction to spread below the ground level. In some cases, due to the presence of obstacles such as the presence of buildings and underground facilities in the neighboring properties, excavations are done vertically. It is obvious that in order to prevent possible accidents, excavation operations must be accompanied by stabilization. If the safety factor [1] is not taken into account in the stabilization design of the excavation wall, it can cause irreparable human and financial losses. The occasional news of nearby buildings toppling during excavation shows the risk-taking and importance of this issue. On the other hand, the factors that are involved in determining the confidence factor also have uncertainty[2], in the sense that with the change of each of these factors, the confidence factor is also changed, as a result, the risk tolerance and risk probability[3] also change. If this issue is ignored in the designs, it can impose unwanted costs. It should be noted that very large reliability coefficients also increase stabilization costs. Therefore, the accurate and informed estimation of the reliability factor, in addition to safety aspects, can also economically reduce the cost of these projects.

    Deep trenching on the Nicol Highway [4] in Singapore is an example of a huge geotechnical project that led to a disaster a few years ago. This excavation was being carried out at a depth of 30 meters and with a width of 10 to 15 meters in Marni clay, with the bracing of the diaphragm wall, when on the afternoon of April 20, 2004, the wind beam on top of it broke and the result was a 110 meter long land fall. which caused the collapse of Nicol highway in that area. Also, the large movement of soil caused an explosion in the gas supply pipes and a fire. 4 people died in this incident. Unfortunately, in recent years, similar incidents have happened in our dear country, Iran. The expansion of excavations and the possibility of such incidents show the importance of this issue. The analysis of geotechnical structures based on risk assessment[5] is a subject that has recently attracted the attention of researchers. The reason for this approach is the existence of non-deterministic parameters or uncertainties in geotechnical issues. Because the existence of uncertainties leads to unreliable designs. Therefore, the degree of uncertainty of the design and the risks caused by this design should be evaluated in order to reduce the amount of damages with risk management [6]. Risk management is the systematic application of management procedures, practices and policies to identify, analyze, evaluate, reduce and monitor risk.. Risk reduction is the use of appropriate methods and management principles to reduce the probability of an event or its adverse consequences, or both. Estimating risk and comparing it with acceptance criteria (quantitative or qualitative) is an integral part of risk management.

    1-2- Statement of research topic

    Researchers have always sought to quantify phenomena and use probabilistic theories to model and analyze them. The quantification of phenomena and the use of probability theories were considered in the 16th and 17th centuries. The issue of risk and its management was also raised a few years after that and it quickly received attention in various sciences, but its current form was raised after 1960, which led to the emergence of insurance. The principles of risk assessment and management have been applied more formally to urban areas at risk of landslides and slope control around highways since the 1970s. In the 1980s, and especially in the 1990s, with the introduction of quantitative methods, pipeline route risk management and especially slope risk management developed. Many researchers such as Warrens (1984), Whitman (1984), Einstein (1988, 1997), Fell (1994), Leroy (1996), Wu et al. (1996), Fell and Hartford (1997), Nadim and Lacasse (1999), Hu et al. (2000) Waltsed et al. (2001), Nadeem et al. (2003), Nadeem and Lacasse (2003, 2004), Hartford and Beecher (2004), and Lee and Jones (2004). have played a role in this development. Recently, studies have been conducted with the aim of improving risk factors, emphasizing the importance of uncertainty analysis and confirming probabilistic methods as a useful tool for decision-making. One of the important features in risk assessment is that subsequent decisions are facilitated by analyzing different risk modes (for example, cost-benefit analysis[7]). This research explains how to use probabilistic methods to describe uncertainty and risk assessment as an analytical tool for decision-making. 1-3- Design based on risk assessment [8] As stated, all engineering designs are faced with uncertainty. Uncertainty is evident in material specifications, operating conditions, engineering models, and so on. In fact, due to these uncertainties, geotechnical engineers consider the design capacity more than the required value of the project. The ratio of capacity to demand (reliability factor) is usually chosen based on experience. This method has major drawbacks. For example, this method is conservative. As a result, the overconfidence factor in the design is unknown. Although conservatism in estimating soil characteristics and forces seems reasonable. Due to the variety of uncertainties, a fixed confidence factor in different problems leads to different failure probabilities. A design based on risk assessment can cover some of the limitations of the definite confidence factor. Design based on risk assessment means trying to quantify the inherent uncertainties of an engineering problem and how to deal with them. "Design based on risk assessment" in geotechnical engineering is divided into two parts: data analysis and model structure. In the data analysis part, uncertainties are identified and quantified using statistical relationships. In the model building phase, mathematical relationships are used to evaluate the effect of uncertainties in calculations. Another result of risk-based design is quantifying the reliability of the structure. This value is called "reliability index [9]".

    1-4- Comparison of traditional methods and probabilistic methods

    The piedra analysis of slopes is traditionally based on determining the reliability coefficient. Geotechnical experts rely heavily on empirical judgments, such as the concept of confidence factor, to assess the stability of a suitable slope for development. The reliability coefficient of slopes is defined as the ratio of the shear capacity at the critical failure level to the shear stress on that level. In other words, the reliability factor measures the ratio of resistance that must be reduced so that the slope reaches the definite failure point. Recently, it has been found that the value of the confidence factor does not necessarily predict good slope stability performance. One of the limitations of using the confidence factor is the existence of uncertainties in soil resistance parameters. If it is possible to define the variability of the stability analysis input parameters such as adhesion, friction angle and soil specific gravity in the form of probability density, the confidence coefficient of the slope will also follow a probability density.

  • Contents & References of Risk assessment in sustainability of dredging projects by considering uncertainties

    List:

    Chapter One - General. 1

    1-1- Introduction. 2

    1-2- Statement of the research topic. 3

    1-3- Design based on risk assessment. 4

    1-4- Comparison of traditional methods and probabilistic methods. 5

    1-4- The purpose and scope of the research. 5

    1-5- Thesis structure. 6

    Chapter Two - A review of the subject literature on pit analysis and stabilization methods. 8

    2-1- Introduction. 9

    2-2- Conventional excavation and buffering methods. 10

    2-3- well stabilization methods. 11

    2-3-1- Factors affecting the selection of excavation methods. 13

    2-4-causes of rupture in deep excavations. 14

    2-5- Comparing the cost of implementing different well stabilization systems. 15

    2-6- Pit stability analysis methods 16

    2-6-1- Traditional methods of pit stability analysis 16

    2-6-1-1- General limit equilibrium method. 17

    2-6-1-2- Flenius or normal method. 19

    2-6-1-3- Bishop's simplified method. 19

    2-6-1-4- the simplified method of Janbo. 20

    2-6-1-5- Spencer method. 21

    2-6-1-6- Morgenstern-Price method. 23

    2-6-1-7- The method of the group of engineers. 23

    2-6-1-8- Sarma method 24

    2-6-2- Well stability analysis by finite element method. 25

    2-6-3- probabilistic methods of pit stability analysis. 26

    2-7- Summary. 27

    Chapter 3- Management of uncertainty sources and risk-based design. 29

    3-1- Introduction. 30

    3-2- Sources of uncertainty in geotechnical engineering. 31

    3-3- Estimation of average and standard deviation of geotechnical parameters. 33

    3-3-1- The best estimate. 34

    3-3-2- Uncertainty. 34

    3-3-2-1- Calculation of the standard deviation based on the available data 34

    3-3-2-2- Calculation of the standard deviation using the coefficient of variation. 35

    3-3-2-3- Calculation of standard deviation based on the law of three standard deviations 35

    3-4- Risk and safety. 36

    3-5- Methods based on risk assessment. 37

    3-5-1-Benefits of risk assessment. 38

    3-5-2- The role of risk assessment. 38

    3-6- Design based on risk and probability of failure. 39

    3-7- Calculating the probability of failure using reliability analysis. 43

    3-7-1- The method of combining the distribution curve of random variables. 45

    3-7-2- Point estimation method. 45

    3-7-3- First order second anchor method. 46

    3-7-4- Advanced first-order second moment method. 47

    3-7-5- Monte Carlo simulation method. 50

    3-8- Summary. 54

    Chapter 4- Well stability evaluation by Monte Carlo method. 56

    4-1- Introduction. 57

    4-2- Risk assessment process. 57

    4-3- Quantitative assessment of risk in well stability. 60

    4-4- Risk acceptance and tolerability criteria. 61

    4-4-1- Acceptable risk. 61

    4-4-2-unacceptable risk. 61

    4-4-3- tolerable risk. 61

    4-4-4- Making decisions based on risk. 62

    4-5- Risk management in dredging projects. 64

    4-5-1- Risk management process. 64

    4-5-1-1- Risk identification. 64

    4-5-1-2- Risk assessment. 65

    4-5-1-3- risk control. 65

    4-6- Well stability assessment by Monte Carlo simulation method. 66

    4-7- Solving a sample example. 68

    4-7-1- Statistical characteristics and characteristics of nails 69

    4-7-2- The number of repetitions and probability of failure in the Monte Carlo method. 72

    4-8-Sensitivity analysis. 77

    4-9- Parametric analysis. 81

    4-10- Conclusion. 84

    Chapter Five - Conclusion and suggestions. 85

    5-1- Introduction. 86

    5-2- Results. 87

    5-3- Suggestions for future research. 89

    List of references. 91

    Appendix 1-Statistics and probabilities. 96

     

    Source:

     

    Akbari Hamed, Ardalan., Moghadaripour, Mohammad. and Rahmani, Iraj (1390). Reliability analysis of nailed walls using probabilistic Monte Carlo method. Proceedings of the 2nd Reliability Engineering Conference. Tehran, Aerospace Research Institute.

    Taghizadeh Qahi, Ezzatullah (2007). Stabilization of deep excavation walls by nailing method in urban areas. Fine Arts Journal, No. 35, Fall 2017, pp. 51-61. Kasabzadeh, J (2012). Evaluation of soil liquefaction potential by reliability analysis method. Master thesis of civil engineering-soil and foundation mechanics, Faculty of Water and Environmental Engineering.Master thesis of Civil Engineering - Soil and Foundation Mechanics, School of Water and Environmental Engineering, Shahid Beheshti University.

    Monafi Qarabai, S.M. (2017). Investigating the instability of the earthen dam body in safety management using risk assessment. Master's Thesis of Civil Engineering - Soil and Foundation Mechanics, School of Water and Environmental Engineering, Shahid Abbaspur University of Water and Electrical Engineering.

    Manafi Qarabai, Seyyed Masoud., Noorzad, Ali., Mehdavifar, Mohammad Reza. and Bagheri Khalili, Faezeh (2010). Assessment of the instability risk of the earthen dam body by Monte Carlo method (case study: Dosti Dam). The first international conference and the third national conference on dams and hydropower plants. Tehran, http://www.civilica.com/Paper-NCHP03-NCHP03_400.html

     

    Abramson, L. (2002). Slope Stability and Stabilization Methods. McGraw-Hill, New York.

    Ang, A. S., Tang, A. H. (1984). Probability Concepts in Engineering Planning and Design. Inc., New York, vol. vol. II, 1984.

    Aven, T., Vinnem, J. E. (2007). Risk Management Principles and Methods-Review and Discussion. Risk Management: With Applications from the Offshore Petroleum Industry, 19-75.

    Baecher, G. B. (1987). Geotechnical Risk Analysis User's Guide (No. FHWA/RD-87-011).

    Baecher, G. B., Christian, J. T. (2005). Reliability and Statistics in Geotechnical Engineering. John Wiley & Sons, New York.

    Box, G. E., Muller, M. E. (1958). A Note on the Generation of Random Normal Deviations. Mathematical Statistics, Vol. 29, pp. 610-611.

    Cao, Z. (2012). Probabilistic Approaches for Geotechnical Site Characterization and Slope Stability Analysis.

    Cardenas, I. C., Halman, J. I. M., & Al-Jibouri, S. H. (2009). An Uncertainty-based Framework to Support Decision-making in Geotechnical Engineering Projects.

    Chandler, D. S., (1996). Monte Carlo Simulation to Evaluate Slope Stability. Conference Proceeding on Uncertainty in the Geological Environment, Wisconsin, Vol. 1, pp. 474-493.

    Chowdhury, j. (2009). Geotechnical Risk Assessment and Hazard Management Guidelines. Principal Engineer Geotechnical.

    Chowdhury, R.N., (1987), Practical Aspects of Probabilistic Studies for Slopes, Soil Slope Instability and Stabilization, Sydney, pp. 299-304.

    Chowdhury, R.N., Xu, D.W. (1995), Geotechnical System Reliability of Slopes. Reliability Engineering and System Safety. Vo1.47, pp. 141-151. Christian, J. T., & Baecher, G. B. (1994). Journal of Geotechnical Engineering, 120 (12), 2180-2207. Landslide Risk Assessment and Management, 64 (1), 65-87. Danka, J. (2011). In Geotechnical Engineering: Proceedings of the 21st European Geotechnical Conference, IOS Press. (2000).Factors of Safety and Reliability in Geotechnical Engineering.Journal of Geotechnical and Geoenvironmental Engineering, Vol. 126, No. 4, pp. 307-316.

    Ergun, M. U. (2008). Deep Excavations. Electronic Journal of Geotechnical Engineering, Available at: www. eje. com/Bouquet08/UfukErgun_ppr. pdf.

    Fell, R. (1994). Landslide Risk Assessment and Acceptable Risk. Canadian Geotechnical Journal, 31 (2), 261-272. Fell, R., & Hartford, D. (1997). Landslide Risk Management. Balkema, 51-110.

    Fell, R., Ho, K. K. S., Lacasse, S., Leroi, E. (2005, May). State of the Art Paper 1-A framework for landslide risk assessment and management. Proceedings of the International Conference on Landslide Risk Management, Vancouver, Canada, Vol. 31.

    Fenton, G. A., Griffiths, D. V. (2008). Risk Assessment in Geotechnical Engineering 480 p. New York: John Wiley & Sons.

    Ferris, G., Samchek, A., and Isherwood, A. (2003) Geotechnical Risk Assessment: Estimating Slope Failure Probability. New Pipeline Technologies, Security, and Safety: pp. 1252-1260.

    FHWA. (2003).

Risk assessment in sustainability of dredging projects by considering uncertainties